Turning an underused section of school grounds into a practical sports facility can make a significant difference to the opportunities available for pupils. 

Our team undertook an artificial grass sports area conversion at a primary school in Hemel Hempstead, with the aim of creating a durable, attractive and versatile outdoor space suitable for PE lessons, playground activities and recreational sports.

The school had previously relied on a natural grass area that became increasingly difficult to use during the wetter months. 

Our task was to transform the space into a dedicated synthetic turf facility while considering drainage, pupil safety and the practical requirements of a busy primary school environment.

Why the School Wanted to Convert Its Existing Grass Area

The project began with a discussion involving the school's site manager and members of the teaching staff.

They explained that the existing grass area was popular during the summer but frequently became muddy and waterlogged during autumn and winter.

This meant that outdoor PE lessons often had to be relocated to the playground or indoor hall, limiting the activities teachers could organise.

The school wanted to make better use of the available outdoor space without introducing a high-maintenance surface.

During our initial assessment, we discussed the advantages of installing a specialist artificial grass system, including improved surface consistency, reduced mud and the ability to accommodate more frequent use.

The teaching staff were particularly interested in creating a multi-purpose area rather than a dedicated football pitch.

They wanted pupils to be able to use the space for small-sided football, general fitness activities, movement exercises and supervised playground games.

With these requirements in mind, we recommended a durable sports-grade synthetic turf system suitable for primary school use.

Designing the New Sports Area

Before beginning construction, our team measured the existing grass area and reviewed the surrounding access routes.

The proposed installation needed to fit comfortably within the available grounds while maintaining appropriate separation from nearby buildings, pathways and playground features.

We discussed the finished layout with the school and agreed to retain a simple rectangular playing area with clearly defined perimeter edges.

The selected artificial grass featured resilient synthetic fibres designed for regular recreational activity, with a specification appropriate for the intended sports and age groups.

We also considered whether an additional shock-absorbing underlay would be beneficial.

Following discussions about the activities planned for the area, we incorporated a suitable performance shockpad beneath the artificial turf to provide additional cushioning and support the playing characteristics of the system.

The final design also included a free-draining foundation and secure perimeter edging to help maintain the condition of the installation.

Preparing the Ground During the School Holidays

To minimise disruption, we arranged for the main construction works to take place during a school holiday period.

Our team began by setting out the proposed sports area and removing the existing turf and topsoil.

The excavation was carried out to the required formation depth, allowing sufficient space for the new aggregate sub-base, regulating layer, shockpad and artificial grass carpet.

Once the ground had been exposed, we inspected the formation for soft spots and unsuitable materials.

Several localised areas required additional excavation and replacement with compacted aggregate to establish a consistent foundation.

We then installed a suitable geotextile separation layer where required, followed by a free-draining crushed stone sub-base.

The aggregate was placed in controlled layers and compacted using specialist equipment.

Particular attention was given to achieving the correct levels and ensuring water could drain through the construction without collecting beneath the finished playing surface.

We also installed perimeter restraints to provide a secure edge for the artificial grass system.

An Unexpected Issue with the Existing Ground

One of the more challenging parts of the project occurred during the excavation stage.

Near one corner of the proposed sports area, we discovered a section of ground that was noticeably softer than the surrounding formation.

Rather than continue laying the sub-base over the unsuitable material, we contacted the school's site manager and explained our findings.

We recommended removing the affected material and replacing it with properly compacted aggregate.

Although this required additional groundwork, it was important to prevent future settlement that could cause unevenness in the artificial grass surface.

The school agreed with our recommendation, and the extra preparation was completed before the main sub-base installation continued.

Fortunately, the issue was limited to a relatively small section, so it did not significantly affect the overall construction programme.

Installing the Artificial Grass Sports Surface

With the foundations completed, our team moved on to installing the shockpad and synthetic turf.

The shockpad was positioned across the prepared base, with individual sections aligned and secured in accordance with the selected system's installation requirements.

We then rolled out the artificial grass carpet, allowing the material to settle before carrying out the final positioning and trimming.

The turf sections were carefully aligned to maintain a consistent pile direction across the entire sports area.

Specialist jointing tape and compatible adhesive were used to secure the carpet seams, creating a continuous playing surface.

Our installers paid close attention to the perimeter details, ensuring the artificial grass was neatly trimmed and secured against the edging restraints.

The surface was then brushed and finished in accordance with the manufacturer's specification, including the application of any required stabilising infill.

We also incorporated simple sports markings to help teachers organise small-sided games and structured PE activities.

How Long Did the Conversion Take?

The artificial grass sports area conversion took approximately three weeks to complete, including excavation, ground improvements, sub-base construction, shockpad installation and artificial turf fitting.

The first week focused on removing the existing natural grass and completing the necessary groundwork.

During the second week, our team installed the drainage foundation, perimeter edging and final regulating layers.

The remaining period involved laying the shockpad, installing the artificial grass, completing the markings and carrying out the final inspections.

We maintained regular communication with the school throughout the project, providing progress updates and confirming when each stage had been completed.

The school was particularly pleased that the main construction activities could be carried out during the holiday period, avoiding disruption to normal lessons.

A New Space for PE Lessons and Playtime

Once the installation was complete, we arranged a final walkthrough with the school's site manager.

We checked the artificial grass joints, perimeter fixings, surface levels and overall finish before handing the area back.

The completed sports area provided a substantial improvement over the original natural grass space, offering a more consistent surface that could be used for a wider range of activities.

The teaching staff were pleased with the flexibility of the new facility, particularly the opportunity to organise outdoor PE sessions without relying as heavily on natural ground conditions.

We also explained that artificial grass still requires routine maintenance, including brushing, debris removal, seam inspections and monitoring of infill levels where applicable.

For our team, the most rewarding aspect of the project was transforming a frequently unusable section of school grounds into a dedicated recreational space that could support pupils' physical activity throughout the academic year.

Artificial Grass Sports Area Installations Across the UK

This primary school project in Hemel Hempstead highlighted the benefits of combining appropriate ground preparation with a carefully selected synthetic turf system.

By addressing the existing drainage and foundation issues before installing the artificial grass, we were able to create a practical sports area designed for regular school use.

We provide artificial grass sports area conversions, synthetic turf installations and school playground surfacing services for educational facilities throughout the UK.

Get in Touch

We aim to get back to you in 1 working day.


Skip to

Privacy Information

Social Links